Explore TEAMS!
|
Student /
CarpScheduleKey 2009 ATDF Milestones Date Event Feb 25 First Meeting with Mr. A and his parents. Feb 27 Identify Client Mar 9 Project Proposal Due Mar 14 Meeting with Mr. A's teacher PDR - 3 Dry run your presentation, check to see if you have completed in enough detail Mar 27 - 31 Preliminary Design Review (PDR) PDR + 1 First parts order due Apr 17 Prototype Hardware Review ("50% functional") May 1 Prototype Hardware & Electronics Review ("80% Functional + Preliminary Testing with Client") May 8 Nearly Final ("90% Functional") Project Tested with client May 15 Nearly Final ("95% Functional") Project "Fair Ready" May 15 Project Poster, Presentation, Brochure & Preliminary Project Report Done May 16 ATDF, Saturday Morning, 8 am - 1 pm in Cumnock Hall May 23 Final report with photo of client using product & final client feedback |